Description of Deliverables:
Document / Hardware / Software

Deliverable Identifier (e.g. TN1, etc.)

Title

Delivery date

Milestone (if applicable)

Document

 

TN1

State of art & list of requirements of stakeholders for mapping an abandoned agricultural land

T0 + 3 months

MS1

Document

 

TN2

Theoretical base of mapping an abandoned agricultural land
PDF document »

T0 + 9 months

MS2

Document

TN3

Database of spatial reference data – description of structure and metadata

T0 + 9 months

MS2

Document

TN5

Map outputs with information on abandoned agricultural land classes

T0 + 21 months

MS3

Document

 

TN6

Theoretical base of proposed algorithm for estimation of biomass stock on abandoned agricultural land, including relevant electronic files

T0 + 18 months

MS3

Document

 

TN7

Models for estimation of biomass stock on abandoned agricultural land, including relevant electronic files

T0 + 21 months

MS3

Document

 

TN8

Innovative methodology of permanent tree biomass inventory on abandoned agricultural land based on optical and SAR satellite data

T0 + 24 months

MS4

Technical data package

TDP

Technical data package containing detailed description of all technical works within the project implementation, including a subset of data for methodology verification and relevant electronic files

T0 + 24 months

MS4

Document

FR

Final report

T0 + 24 months

MS4

Document

ESR

Executive summary report

T0 + 24 months

MS4

Document

 

CCD

Contract closure document

T0 + 24 months

MS4

Remarks: Progress report will be delivered each 3 months. According to ESA comments, previous TN4 (progress report after 12 months) was removed as it is mandatory activity of the reporting system.